Multi-family Residential
Phoenix, AZ
Trade scheduling conflict caught 11 days before impact
Project: 84-unit multi-family residential, mid-size GC, Procore-managed. Week 8 of a 52-week schedule. Three active trades on-site (framing, plumbing rough-in, HVAC).
The challenge: Plumbing crew had fallen 4 days behind baseline on levels 2 and 3. The daily logs documented the shortfall but nobody had synthesized it against the HVAC start date. Both trades were scheduled in the same space starting week 10.
Detection: Girdergrove flagged the plumbing drift at day 3 of the pattern (daily log mentions: "short crew, partial scope only"). Risk flag: "Plumbing baseline drift, 4d behind. HVAC look-ahead conflict: 2 trades scheduled same zone, week 10." Alert at day 11 before HVAC mobilization.
Outcome: GC reshuffled HVAC mobilization by 5 days. No schedule compression, no premium labor cost.